| Methods
of Payments for the Injection Contractor
by John
Trout
On most
construction applications it is fairly simple to prepare a specification
which assures that the contractor is paid only for what he completes
in a satisfactory manner and leaves little room for misunderstandings.
However, since quantities
on an injection project vary often and dramatically, flexibility in
contract provisions is essential to avoid costly renegotiations. Factors
such as disappointing results, results more promising than anticipating,
discovery of additional deterioration, realization that designated
cracks are in fact uninjectable spalls, loss of funds, etc. affect
injection quantities. With owner and contractor acting in good faith
it is often difficult to resolve quantity changes. At the hands of
an unscrupulous contractor, the owner is precariously and unnecessarily
vulnerable. It is important to select a payment method which protects
the owner yet assures the contractor of full compensation for his work.
This flexibility can be provided by unit prices but there are pitfalls
if the specifier is not careful.
Methods
of payment to contractors for injection work have included:
- Lump
sum. Contractor
views overall project and submits a firm quotation to complete
the job. This option appears to be the most attractive and if it
is possible to identify the exact cracks and footage to be included,
the lump sum works. However, such specific knowledge is seldom
available and problems result. For example, if a closer inspection
from scaffolding reveals additional cracks which require injection,
how is the contractor to be compensated for the additional work?
In other instances cracks which appeared to be injectable were,
under closer inspection, found to be spalls which are not injectable.
In either instance negotiations must follow as the lump sum number
becomes moot.
- Per
liter. Contractor
is paid a unit price per liter of resin consumed. The per liter
option is probably the most fraught with difficulty for the owner
and the responsible contractor. If payment is based upon per liter
of "resin" used it will no doubt be interpreted by the
contractor as including the paste for capping the crack. This interpretation
will often result in the use of excessive paste for the seal, leaving
the wall plastered with epoxy at great expense to the owner. Though
the paste may be specifically excluded, problems remain. Is compensation
for resin "used" or resin "injected" into the
fault. Much resin can be "used" in the course of frequent
clean?up, ratio checks, purging of lines to bring up fresh material,
etc. If payment is limited to resin actually injected into the
crack, the unit price quoted per liter will be very high. An unscrupulous
contractor would have to be constantly observed to prevent deliberate
waste. This is seldom easy. The unit price per liter may work very
well with a responsible contractor in place, but the responsible
contractor will seldom be low bidder on such a project since he
cannot depend upon waste to pad his quantities.
- Per
linear meter. Cracks
are simply measured for payment as the work progresses. It eliminates
anxieties regarding resin consumption. This system works very
nicely so long as the estimated quantities are close to reality.
However, if the estimated amount vary dramatically from the amount
of work actually required, the owner or contractor will be seeking
adjustments.
- Mobilization
+ linear meter is
a refinement of the straight linear meter approach. It simply obviates
any need for adjustments should quantities vary in either direction
no matter the amount. The contractors cost of mobilizing is separate
and is not amortized over this unit quantities. An adjustment is
not appropriate.
- Time
+ material. This
approach is used too often. Unit prices can be developed to anticipate
most conditions. Be reluctant to use time + material with any other
than a most reputable contractor.
Approach #4, mobilization
+ linear meter is recommended wherever possible for the best contractor
/ owner relations. Using this method of payment and a strong quality
control program based upon frequent coring, the owner is assured that
he will pay for only what he gets and get the quality which he has
paid for.
For a copy of this
document in printable PDF format, please download
Methods
of Payments for the Injection Contractor
Viewing a PDF format file requires Adobe Acrobat Reader, which is a free downloadable software available by clicking here:
|